Long Phu 1 Thermal Power Plant

Project  Long Phú 1 Thermal Power Plant
1 Contractor PTSC (2011-2012)
2 Work done Soil improvement by Vacumm preloading & PVD

Pre-fabricate Vertical Drain PVD installation 18-20m.

3 Quantity 70 ha
4 Time From 20/1/2011 to 30/5/2012
5 Location Xã Long Đức, huyện Long Phú, tỉnh Sóc Trăng

Today 5/12, in Soc Trang, Deputy Prime Minister Truong Vinh Trong attended a ceremony to launch the construction of thermal power plant in Long Phu 1 has a capacity of 1,200 MW with a total investment of $ 1.2 billion.

The project is located in Long Duc commune, Long Phu District, by the National Oil and Gas Group Vietnam as an investor. Long Phu Power Plant 1 of Long Phu Power Centre was approved by the Ministry of Industry and Trade planned into 3 plants with a total capacity of 4,400 MW.

Long Phu Power Plant 1 is a project of the General Map VI was approved by the government and is expected to be completed, the generator unit 1 in 2014, Unit 2 in 2015. The project has total value of $ 1.2 billion.

The plant uses technology pulverized coal fired supercritical parameters were applied for the first time in Vietnam with high-performance, always make sure the conditions emissions standards internationally Vietnam and current.

Deputy Prime Minister Truong Vinh Trong stressed, Project Long Phu Power Plant 1 is extremely important, not only contribute to ensuring national energy security but also contribute to economic development and social, economic restructuring and regional Soc Trang Mekong Delta.

Deputy Prime Minister asked the investors with the relevant units in close coordination during project implementation; especially should they take care of environmental protection; occupational safety, resolving issues arising … ensure that projects are implemented and completed according to quality requirements and schedule already set.

PVD-LP1